About the Project

In an ongoing effort to provide quality wireless service, T-Mobile has identified your community as one that will benefit from improved network coverage. 

Milestone Communications is proposing a wireless telecommunications facility at Fauquier High School, addressed 705 Waterloo Road, Warrenton, VA 20186. 

The proposal is for a 130-foot monopole and will include ground equipment required to operate the facility.   This equipment will be located at the base of the structure in a secure fenced area. T-Mobile will be the first wireless carrier to locate on the proposed tower.

Update #1:  There are two upcoming community events: 

Online Town Hall: On Thursday, August 20th @ 6:30 pm we will hold an online Town Hall webinar consisting of a short presentation followed by a question and answer time.  Please go to the Town Hall page to complete the required registration.

Community Balloon Fly – On Saturday, August 15th from 8:00 am to 12:00 pm with a weather delay date of Sunday, August 16th from 8:00 to 12:00 pm. The decision will be made based on the weather forecast and posted here on the Home Page by 6 pm night before. A balloon will be flown at the proposed location and height to provide a visual reference for the tower.

Update #2:  We are moving forward with the balloon fly tomorrow from 8:00 am to 12:00 pm. 

Update #3: Our Commission Permit (CP 2020-01) and Special Use Permit (SUP 2020-01) will go before the Planning Commission, Tuesday, September 15th @ 7:00 pm.  

Update#4Our Commission Permit (CP 2020-01) and Special Use Permit (SUP 2020-01) will go before the Town Council, Tuesday, October 13th @ 7:00 pm.

Update #5: Commission Permit (CP 2020-01) and Special Use Permit (SUP 2020-01) were approved by both the Planning Commission and the Town Council.

Our Process

1. Due Diligence 

Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.

2. Land Use

Special Use Permit, Community Meeting, Staff Review, Planning Commission, Town Council.

3. Permitting 

Conduct bid walk With contractors and school representatives, submit site plan and building permit applications.

4. Construction 

Tower construction = 4-6 weeks  | Carrier construction = 4-6 weeks on average

On-site supervision by Construction Manager | Schedule with schools to minimize disturbance to student activities.

 

5. Site Maintenance

Four visits per year for site maintenance |Remove trash, debris, check signage. 

Annual RF testing | 2-4 visits per year for carrier modifications. 

About Us

With over 15 years experience, Milestone Communications is the leading developer of wireless infrastructure and cell towers in partnership with school, government and utility landowners.